Scope
This standard addresses the requirements for performing verification by testing of space segment elements and space segment equipment on ground prior to launch. The document is applicable for tests performed on qualification models, flight models (tested at acceptance level) and protoflight models.
The standard provides:
- Requirements for test program and test management,
- Requirements for retesting,
- Requirements for redundancy testing,
- Requirements for environmental tests,
- General requirements for functional and performance tests,
- Requirements for qualification, acceptance, and protoflight testing including qualification, acceptance, and protoflight models’ test margins and duration,
- Requirements for test factors, test condition, test tolerances, and test accuracies,
- General requirements for development tests pertinent to the start of the qualification test program,
- Content of the necessary documentation for testing activities (e.g. DRD).
Due to the specific aspects of the following types of test, this Standard does not address:
- Space system testing (i.e. testing above space segment element), in particular the system validation test,
- In-orbit testing,
- Testing of space segment subsystems,
- Testing of hardware below space segment equipment levels (including assembly, parts, and components),
- Testing of stand-alone software,
- Qualification testing of two-phase heat transport equipment,
- Tests of launcher segment, subsystem and equipment, and launch facilities,
- Tests of facilities and ground support equipment,
- Tests of ground segment.
This standard may be tailored for the specific characteristic and constrains of a space project in conformance with ECSS-S-ST-00. Annex D gives guidelines for performing this tailoring.
Attachments
Md5 checksum .doc file = 908A4C2E7169C9ED30A5B6E32EA8D432
Md5 checksum .pdf file = 0A2A203E6FB30990466ED6AA7815F1CC
DRDs of this standard:
- ECSS-E-ST-10-03C(1June2012)AnnexA_Assembly, integration and test plan (AITP)
- ECSS-E-ST-10-03C(1June2012)AnnexB_Test specification (TSPE)
- ECSS-E-ST-10-03C(1June2012)AnnexC_Test procedure (TPRO)
This Standard cancels and replaces ECSS-E-10-03A (15 February 2002)